Hi Gurus,
I am stuck in a situation where the Error Message BP603 while creating a PO for a wbs at level 2.
IN cj30 , i found out that Budget = 69500000 and assigned = 69950772
if i create a PO OF even .30 (thirty paisa) the budget exceeded amount = 450772.35, which is actually the diffrecene betweenn assigned and Budgeted values.
Now we are not able to raise any PO
Below is tolerance limit
please key in your valuable inputs.
Regards
Rohit