Hi fellows
Actually I have the following setting dates
Then I put more resources to its "Engineering Documents" and got the following scenario
Now the activity "Document Engineering" ending 4/11/2014 and "Mobilizing Equipment" activity begins 14/11/2014, namely that there is a space of 10 days and WBS "Mov. / Const. PROVIC Facilities "It is not doing the reprogramming