Dear All,
Following query already discussed in the forum. But i am not getting "POC actual" & "BCWP" the result for my case scenario.
I am using Plan method as "Time proportional" and Actual method "work" at activity level & maintained POC weight manually.
At WBS level, I am maintaining Plan method as "Time Propartion" and Actual method as "Time Proportion".
Setting for Progress Version: Plan Version not maintained.
EV Basis : Budget (Active Project, Overall Value)
POC Weighting: Weight (Active Project)
Planing Type: Basic Dates
Early/Late: Early possible
Actual method and ref. plan method are selected.
Confirmation is done and run CNE1 and CNE5. but i didn't get "POC actual" & "BCWP".
After Final confirmation i got the result, but at partial confirmation it didn't show the value.
Regards.