Hi Experts,
My client currently following internal order, now they are going to migrate to Project Systems module. My concern is …the cost booked against to Internal Order like Material cost, Service cost, Transport cost….etc , in Project system Project structure will be divided like Material Wbs , Service WBS, Transport WBS….etc. under one Project. when we do migrate the data from Internal Oder to Project System.
Material cost will be transferred to Material WBS element
Service Cost will be transferred to Service WBS element
Transport cost will be transferred to Transport WBS element..
how to do this ...
Regards,
Kishore