Dear Gurus,
I need some help for date scheduling . I am doing Backward scheduling in my project. My network start date is 03.11.2014 and end date is 20.11.2014. I have assigned 4 Activities 1) Internal activity 2) External activity 3) Service 4) General cost. PFA screen shot for the same.
Request you to please help me on this issue.
Question:-
1) My external activity(PS02) it is in critical. How it is possible???? Its having start date at 12.11.2014 .
2) PS02 and PS04 both are external activities but dates are different. Earliest start/ finish & Latest Start/Finish.
3) Is critical activity is based on float?????
4) My network start date is 03.11.2014 and my activity PS02 still is in critical????? how it is possible??? that activity still have 9 days to start.??