Plan Actual reporting displays totals at Network level and not Activity

$
0
0

Hi,

 

When I create a project manually with Network activities. Add plan and actuals data against the Activities. I can view totals data down to the Network Activity level when running e.g. v Plan/Actual/Variance.

 

However, projects created automatically via a sales order - the data only breaks down to totals at Network level. Even though the plan and actuals are maintained as per above, at Activity level, these projects when displayed in S_ALR_87013532 only display totals down to Network level.

 

Any ideas why?

 