Hi All
We have a requirement to apply overheads (CJ44) to projects using the standard costing sheet which include expenses and assets ("1" series accounts). Is this even possible?
These assets have been defined as Cost Element 90 and have been included in the Cost Element group in the Calculation Base of the Costing Sheet.
All input is appreciated.
Regards
Vernon