PS Budget change from annual to Overall

$
0
0

Hi all,

 

I have made some changes in the configuration of Budget availability Control. We have set the follwoing:

 

- Tcode OPSB Overall and annual values.
- Tcode OPS9. In Time frame box there are checked both the flag "total" and "annual" values.

  - Tcode OPS9. In the availability control box we set the indicator "Overall".

 

After changing this in productive system we executed OPSX and CJEN to reconstruct the data. However the budget already entered as annual in year 2014 is not showed as overall value. Therefore we cannot make a PO or financial posting with those WBS since the system,ms say that they are execeeded.

 

1. Is there anty inconsuistency in my configuration?

2. How to convert the current budget to overall in the WBSs since the budget was entered as annual?

 

Please advice

 

Kind regards