Asset acquisition with WBS assignment posting in MIGO actual values not capturing

$
0
0

hello gurus

 

here is i am facing new issue on Asset Procurement .

 

 

I create a wbs element X

 

for that wbs element i maintianed 100 dollars budget

 

at the time of PO creation for Asset acquisition 60 dollars , in my PS report showing like below.

 

WBS elementBudgetCommitmentActualsBalance
X10060040

 

 

after with reference of PO , Asset acquisition in MIGO , the asset value wbs element not capturing in actual,that commitment values going to again main budget after MIGO postings , and my report showing like below

 

 

WBS elementBudgetCommitmentActualsBalance
X10000100

 

 

please suggest me the sollution.