WBS Budget Exceed Error while editing Qty as BUDGET is Available

$
0
0

Hi Gurus,

 

We are facing WBS Budget Exceeded error while changing the Qty, as the required budget is available as per report S_ALR_87013558.

 

When a PO is created the budget is consumed, but in COOI table the quantities and values were not updated correctly as per PO.

 

Account Assignment is P, D...............When ever the Service Line items Quantities were changed "Budget Exceeded error occur" but still there is the required budget available.

 

As i have run CJBW, CJEN, CJBV for the following Projects.

 

Please find the screenshot of COOI table, as the quantities are not updated and value were available( Qty: 0.000 / Value: 297,453.61) the remaining top 2 fields were blanks which were available in EKKN.  Please provide your valuable info on this issue.

 

COOI.png

 

Regards

Naveen