Dear Expert,
We are working with project system assigning maintenance order to WBS through of t-code ADPMPS.
When we run the any report from PS (e.g. S_ALR_87013558) we find the values below in one WBS:
1) Budget/Actual/Rem.Plan/Assigned/Available (S_ALR_87013558)
Budget = 428000, Actual = 0, Commitment = 65936, RemOrdPlan = 107960, Assigned = 173896, Available = 254104
To this scenario I have just one maintenance order assigned to this WBS.
However when I go into any maintenance cost report I cannot find the cost as shown on PS report.
My planned cost on MO is $ 123000 (commitment and planned). Even any report that I run to this order I can not identify the values as shown on column total assigned on PS $ 173896 (commitment $ 65936 + RemOrdPlan $ 107960).
Does anyone have any suggestion/explanation to this difference?
See screenshot below
Wagner Silva