How to delete the PR generated by SAP when network activity released

$
0
0

Dear Experts,

 

I have a scenarion where dueing the material BOM transfer ( CN33) we choose Purreq+ Reservation for WBS indicator for all the "Q" stock . The reason being we want the system to generate the PR when the corresponding actvity is released.

 

However in some times, we have transfered stock from plant to project and we don't need the PR anympore. In that case i want the PR to be cancelled OR closed OR Deleted

 

However if I delete the material line item in the network activity, system can delete the PR but we don't want that as i need to issue this material in to project

 

Hence I would want to set Closed in the PR but , the filed is not open for user input ioin CN52N

 

If i created PR directly without from activity RELEASE status. thene I'm able to set the closed indicator

 

Hence please let me know if anyone know is it SAP STD and doesn't allow to do that?

 

Or is there any SPRO seetings. I did check the PR layout setting and the clsoed indicator set as optional. But in ME52N it doesnt allow to set

 

Your reply is greatly appriciated

 

Srinvasaa