Hi Experts,

 

I need your help to sort out the issue let me explain:

 


Availability Budget of WBS element number XXXX is 200 $.

PO raised for the same WBS for 200 $.

 

 

User has decreased the budget from 200 to 150. Now PO amount 50 $ has been exceeded the actual budget.

 

Requirement is while doing MIGO it should not allow to post the exceeded amount for PO and expecting to throw an error saying that budget 50 $ has been exceeded for WBS element XXX.

 