Hi All,
I have issue in CJ88, my scenario is as below
1) Project created & released
2) FXA settlement rule assigned to all WBS
3) Cost booked to Activity & WBS (By confirmation & FB60)
4) Run WIP by KKA2
5) Done periodic settlement by CJ88 (at project level)
6) After Project completed
7) Assigned status TECHO to Project
8) Run KKA2 again
9) Run CJ88 for final settlement (at project level)
After run CJ88 at both the time "RECEIVER" (fix asset ) not capturing in CJ88
Thanks ,
Virendra