Quantcast
Channel: SCN : Discussion List - SAP Project Systems (SAP PS)
Viewing all articles
Browse latest Browse all 2586

Scheduling Dates in SAP-PS

$
0
0

Hi fellows,

 

At present I have the following Work Plan, I don´t have any constraints in dates

Presentación2.jpg

Now, I need rescheduling the activity "Drawings", before this activity had a duration of 9 days, now the new duration is 4 days, after that I programmed and I got this Work Plan,

Presentación4.jpg

Now with that programing, I have the followings problems:

 

- The critical path is not correct

- The calculation is bad, because the activity "Civil Activities" must start in 27/01 and not 30/01

 

Thanks in advance


Viewing all articles
Browse latest Browse all 2586

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>