Hi
I am trying to transfer budget from one project to another using CJ34.
For this I had annual budget of 2,906,076.00 and released budget is 2,906,076.00, as budget is released 100%. I had reverted some amount back from CJ32. Now released budget is 2,893,076.00 and available budget is 13,000/-
Now I am trying to transfer it but it show an error "BQ004 annual budget is less than the distributed budget"
for this I had checked distributed budget column in CJ33 and Found that distributed budget is 2,893,076.00 and same time when i refer S_ALR_87013559 report distributed budget come 2,906,076/-.
I had run CJEN and CJBN but it doesn't make any change.
Please Help.
Regards
Varun