Hi'
I have a setup where WBS level1 is a Billing element.
WBS level 2-3 are Acc. elements
Settlement Rule for Billing element are maintained manual.
Settlement Rule for Acc. elements are copyed from superior rule.
I have generated Settlement rule, the projects are "running", the first settlement has been sucesfully completed.
Now the organisation is changed and the Settlement rule should have a different Profit center.
I put an end period at the Settlement rule at WBS level 1.
I create a new Settlement Rule at WBS level 1.
I put an end period at the generated Settlement rule at WBS level 2-3.
Now I want to generate Settlement Rule again at WBS level 2-3.
That is not possible because a settlement rule already exist.
What can I do to get a new and updated Settlement Rule at WBS level 2-3?
Thank you in advance for advice!
Kind regards
Lone Würtz