Changes to Report Painter Program 12KST1G

$
0
0

Hi all,

 

I have created a copy of the program 12KST1G to Z12KST1G.  I have a requirement of adding two new columns to the end of the report.  I have done that.  Now, my problem is I need to restrict what is shown in those columns.  One requirement is that only show information from 2015 and forward.  That is done.  BUT, I need to only show certain cost elements in these columns.  I am editing the form in CJE5 and I created a copy of the report in CJE3.

 

I've searched around, but have not been able to find an answer.

 

Is this possible?

 