Hi Experts,
In the report S_ALR_870*, we are seeing different commitment in the commitments column. But when we see the Service Purchase orders for this project, we are not able to see the same commitment. One thing i would like to share you that We have changed the WBS profit center in the middle of the project and some sevice PO having old profit center . when we ammend these PO it is hitting double commitment in PS ( Table COOI). Now we realised our mistake and we want to correct the entries.
Please let me know any correction program for above issue. I had tried correction program RKANBU01, RKACOR04 ,RKACOR10 but no result.
Thanks,
KP