Hi experts,
I need you help to find another way to create a confirmation in PS, actually i use the CN25 for create confirmations. But the project structure and
the number of confirmations are very big, near to 700 different combinations of network, activities and Activity types, then for insert the work progress
i need execute the same transaction a very high number of times, because 700 is the number for one project and the client has multiple projects, 50th in average by year.
With this, my trouble is the time for the execution of confirmations, i need another option for register the work progress and of preference that are not PS transaction, because other problem is that when i attemp make the confirmation, in some cases i can't because other user have in use that project network. I hope you can help me with this.
Regards.
Iván BL