Dear All,
We have a scenario for fabrication industry. Where client want to plan material procurement in advance for manufacture FG. But BOM of FG will come in later stage when design phase get finished in phases. Initial for cost planning and material procurement planning, they are finding out requirement of material quantities and costing happened on it. This material is planned for procurement, while the BOM will prepared in later design stage. FG are assigned to project activities, and project MRP will give planned orders. these material bom will rolled cost to activities, cost will get doubled and material too. How to handle this scenario, Any standard solution.