Hi All,
Our client need a report of Open commitment as on date like as FBL3N.
If we check the CJI5 report , once the MIGO & MIRO is completed the commitment becomes zero but user wants to check the commitment as on backdated period.
If user post the migo & miro on 06/30/2015 so commitment is zero on 06/30/2015 but user wants to see those same commitment as open on 06/29/2015. Do we have any standard report or table to track such commitment on backdate.
We refer the CJI3 report for actual cost spend on projects but this reports apears as line item wise. Do we have any standard report of summarisation (Total) of actual cost spend on projects. User needs to download the line item wise data in spreadsheet and have to summarise all the data projectwise.
Reply asap.
Thanks & Regards,
SAP_Fi_Cn