AVAC Launch scenerios in PS

$
0
0

HI Gurus,

 

I'm puzzled here, as I have done everything to activate AVAC for all my projects, but it only actvates in 1 scenario of project creation (and fails for the other).

 

Scenario - 1


CJ20N I create a project structure without Network header and activities. release WBS. Save

IM52 Distribute budget to it

CJBV Activate AVAC

CJ20N Add Networkheader to project, add Network activity, add material compoment for price that is valued over budget.

Release Network header + Network, Save.

In this scenario I get my Error message saying that I'm over budget

 

Scenario - 2


CJ20N I create a project structure with Network header, activities and material component priced over budget straight away

IM52 Distribute budget to it

CJBV Activate AVAC

CJ20N Release All: WBS, Networkheader + Network, Save.

In this scenario I succesfully raise a Purchase Requisition above budget.

 

Please can some one help me to understand why Error message is not showing up in Snerio 2.??


here is my config

 

Picture1.png