Hi PS Experts,
This is my second query on the same subject but with different issue, i am not able to catch the exact reason for this.
I have created Service PR against WBS amounting to 5,000,000 with Qty as 10 AU. At this stage report (S_ALR_87013533) perfectly showing me commitment of 5,000,000.
But While posting partial PO against the same WBS of 500,000 with Qty as 1 AU, the report reverses all the commitment to ZERO which is wrong.
I have created one report on report painter which should show commitment through PR (Value Type = 21) and commitment through PO (Value Type = 22) to check where exactly is the issue.
Logically, the system should behave like as soon as i post PO of 500,000, system should show PR commitment as 4,500,000 (reduced by 500,000) and PO commitment as 500,000 (increased by 500,000) but it blanks out everything. Its clearly a loose of control over budgeting (AVAC).
Can anyone kindly give me clues to solve this issue?
Regards,
Zain Bashir