Total Critical Path duration on activities

$
0
0

Hi All,

 

I have created project on which I have created activities which showing critical path but my query is that is there any field from which I can get total duration of critical path. I have highlighted below days of critical path which I want to know how many total days critical path is calculated so does in SAP standard any filed is available how for calculating total critical path duration.

 

Critical_Path.PNG

 

Regards,

Faizan Khalil