Quantcast
Channel: SCN : Discussion List - SAP Project Systems (SAP PS)
Viewing all articles
Browse latest Browse all 2586

Project Forecast cost and Project Cash Managemnt

$
0
0

Hi,

 

We are having Project with

1. valuated stock (Stock Item)

2. only with WBS elements and without network activities and scheduling - All material / service PR raised through MM transaction ME51n with a/c assignment WBS elements 

 

and Having requirement of

Project Forecast cost  - For forecast cost calculation

Project Cash Management - Tp track the payments for project (To get it in SAP standard Report)

 

As per SAP Project forecast cost and Project cash management SAP supports only for

1. Non stock items

2. Plan cost is raised through network activities

3. If project is with scheduling functionality

 

Can anybody tell me if it can be done as per the requirement.

 

Regards,

 

Pradeep


Viewing all articles
Browse latest Browse all 2586

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>