Quantcast
Channel: SCN : Discussion List - SAP Project Systems (SAP PS)
Viewing all articles
Browse latest Browse all 2586

Requirement Grouping - Budget Process

$
0
0

Dear Experts,

 

Need your inputs on below points.

 

Our client is wishing to use requirement grouping,

 

1. Create Project structure with all WBS and Activities.

1.1 Maintain Grouping indicator (2 - Grouping for selected MRP groups)

1.2 Assign MRP group with Project and plant.

1.2 MRP run (on Grouping WBS)

1.3 PR's created on Grouping WBS and Receive stock on grouping wbs.

1.4 Issue based on Reservations created on individual wbs elements.

 

Here, It is required to maintain budget at Grouping WBS as well as individual WBS's. Budget at Grouping WBS for taking inventory in Grouping WBS and at indidual wbs for issue stock based on there material requirements. Client is not happy to maintain Budget at both levels. Although after distribution of requirement to individual wbs would Credit the budget at Grouping WBS  Is it possible for system not to check Budget on individual wbs element ( Grouping WBS ).

 

I have implemented this process first time. Also suggest if you can foresee any issues in this process.

 

Regards

Gaurav Ahuja


Viewing all articles
Browse latest Browse all 2586

Trending Articles