Hello, Experts
In project System, i am creating project with two or more networks within their respected WBS element.
I am giving following data in my project:
Project Definition:
Start Date:1.4.2011
Scheduling Scenario: Free scheduling
Plan.meth/basic:Strict Bottom Up(Without Dates of higher level WBS)
Plan.meth/fcst:Strict Bottom Up(Without Dates of higher level WBS)
Network 1:
Start Date: 1.4.2011
Scheduling Type: Forward
Planning Type: Basic Dates
Schedule Automatic
Network 2:
Start Date: 15.5.2013
Scheduling Type: Forward
Planning Type: Basic Dates
Schedule Automatic
Now my query is:
When i save my project, Network 1 takes the project end date while Network 2 takes the project definitions start date and freeze that date in activites below Network 2. Some times Network 2 does not calculate end date from the duration given in the activity below that network.
Please Give me your suggestion to resolve this issue.......
Regards
Niki