MRP Controller

$
0
0

Hello Expert,

i have done setting of network profile in OPUU based on MRP controller blank,

when we creating project from template system ask for mrp controller its standard behavior of sap ok

 

but when we create PR for non stock materails will MRP copied in item level menas if we see the PR in ME52n MRP is blank for this PR.

 

Requirement is MRP shuld be copied in PR so any customize is required? please suggest?

 

Regards,

Sanjeev