Dear Friends,
whenever we change in conditions of the PO, system is not checking budget for the same.
I do have Account Assignment WBS provided in PO. with AVAC activated on same.
take an example
WBS Budget Rs.100.00
PR Created RS. 90.00 Acc.Asgnmt. WBS
PO Created RS. 98.00 WRT PR+Conditions
Now PO Conditions need to change
PO Change Rs.105.00 updated
Commitment value updated in COOI table, but system skipped Budget checking
Please let me know Why system behave like this??