WBS with Budget in Interface

$
0
0

Hi,

 

We have a 3rd party tool for time management and the interface sends only the valid WBS element to the 3rd party tool for entering time.

The WBS with status DLFL, CLSD, TECO & ISBD is not sent to the tool as required..

 

But now we are facing an issue because of status ISBD..

 

As per Standard SAP, ISBD is getting triggered in WBS elements when it reaches its first tolerance limit (80% is our 1st tolerance limit)..

So, we are not able to use the remaining 25% of the budget (105% is our 3rd tolerance limit) for the Time management tool.

 

It is not possible to change the SAP standard behavior of ISBD to 3rd tolerance limit...

 

Can you please suggest a status or solution where the 3rd party tool will receive all the WBS Elements which has 105% of budget value.

 

Thanks,