Hi,
We're trying to allocate a work center to an internal activity of our project in Project Builder and calculate the activity duration required for the number of work hours specified. This works fine for an individual work center (eg. CNC EDM1, CNC EDM2, etc.) but when we assign a group work center (eg. CNC EDM), it is still considering it as an individual work center and calculating the duration accordingly.
We have created the hierarchy in CR21, but it only recognizes it in CM01 when we put a check on Cumulation of Reqmts and Cumulation of Capacity, and give the hierarchy name. We would prefer to run this planning from the Project Builder itself.
For the group work center capacity if we assign number of individual capacities as more than 1, then it doesn't help if the individual work centers have different capacities.
Any suggestions?
Thank you,
Pratap