Dear All ,
Above warning message appear while assigning budget by CJ30. We have Controlling Area currency INR & Company code currency AED . So done budget profile as below . Project currency is also AED.
Its till allow me to Save the budget but not understand why this message is appear . Check all related configuration setting & also on SCN but no suitable answer found . Let me know if anyone face such issue .
Thanks
Virendra .