'Availability control activated without suitable budget' warning message while assigning Budget

$
0
0

Dear All ,

Above warning message appear while assigning budget by CJ30. We have Controlling Area currency INR  &  Company code currency AED . So done budget profile as below . Project currency is also AED.

BUD profile.JPG

 

Its till allow me to Save the budget but not understand why this message is appear . Check  all related configuration setting  & also on SCN but no suitable answer found . Let me know if anyone face such issue .

 

Thanks

Virendra .