Hi All,
I am working with progress analysis and getting the values POC (plan, actual), but not getting BCWS / BCWP values. I'm using measuring method for multiple activities which are TIME PROPORTIONAL, COST PROPORTIONAL, DEGREE OF COMPLETION and ACTUAL PLAN. I had already maintained the required Customizing for this and we have costs planned and posted at activity level.
Next, the Customization I maintained is :
1. Created Progress Version 100 with exclusive use 'Progress
Analysis'. I have selected Plan & Actual check boxes.
2. Settings for Progress Version-
a) Plan version - '0'
b) EV basis - Cost plan (active project, total values)
c) POC weighting - Weight (active project )
d) Planning type - Basic dates
e) Early / Late - Earliest possible
f) Both reference boxes selected
3. SKFs- I created three SKFs & assigned to Val. Categories.
4. Haven't maintained the default measurement method but maintained in CJ20N against Activities with Time proportional method.
5. Created progress cost element, maintained default, created Cost element group and assigned to value category.
6. In this cost element group, I have not assigned any other cost elements
Before running CNE5, I have also run CNE1 but still not able to obtain BCWS / BCWP values. Can someone help me in getting the BCWS / BCWP?
Regards,
Faizan