Hi,
We would like to limit the Plant the user can enter when planning a Material Component for an Activity to the one the upper Activity, Network, WBS or Project Definition was created on (or at least to Plants within the same Company code the aforementioned objects where created on).
Right now, the Plant takes the one we want by default, but the user can change it even to Plants of different Company codes.
Example:
In the Activity's Component overview:
In the Activity header:
As you can see, by default, Plant 2101 is set (Components/Items 0020 onward), this is the Activity and superior objects Plant's [<- WHAT WE ALWAYS WANT].
But Item/Component 0010 was allowed to be set in 3100 Plant, a plant for another totally different Company code [<- WANT WE WANT TO FORBID].
Thanks in advance for any help,