Dear experts,

 

I wanted to check on a concept if anyone has worked on.

A typical MTO scenario creates a project for every Sale order and network with/without WBS as per standard template.(SD/PS indicator)

 

Networks assigned to materials is direct assignment of networks.

 

The ideas i need is for the below concept:

 

Sale order has a free text line item (Position type 1)

I want to generate a WBS and network for this line item at level 1

 

Sale order has now an actual material line item ( billable and deliverable) (Position type 2)

I want to generate a WBS and network for this line item at level 2

 

I can have several position type 2 and position type 1 line items in a sale order

 

How do you think we can achieve creation of project structure based on position type of sale order as per different levels?

 

Develop a user exit for the sale order?

 

Cheers