Hi All,
My Project is investment project without investment management.
My user wants the WBS to be closed in AUC status. He has earlier closed one WBS in AUC status in year 2012.
Both positive case & current WBS belong to same project.
Can anybody explain what is the procedure & Precautions to be taken to do so.
Please find attached doc.
NOTE: The positive case of WBS in AUC status was closed in year 2012
The current WBS they are closing in this year 2016.
Issue is in closing a particular WBS of the project.
I am getting error message " Balance of WBS is not zero"
PROCEDURE: settle the object before you close it.
Thanks & Regards,
Sudhindra