HI PS Gurus,
Need urgent help !!
Is it possible to use Milestone trend analysis for Progess analysis without creating project version. Also is there any method for Progress analysis without creating project version.
My project has only WBS no activities, i have put the dates and milestones with % of completion, i have put actual dates in some milestone and i used MTA expecting to get planned Vs actual trend but it didn't happened.
My requirement is to get a progress analysis with Planned Vs Actual.
Regards
Prabhat