Cancelled network activity confirmation but actual hours still capture

$
0
0

Dear all,

 

I have executed CN29 to cancel confirmation on the network activity and the status of the network activity is now REL, however there is 22.1 H still capture as actual and also there is forecast hours.

 

1.png

 

Could you please advise on this? How to remove the actual hours?

 

Thanks and regards,

Jessie