Hello All,

 

We need to create project (with 4 level of WBS elements) in SAP PS sytem with reference to template.

 

I have used FM- CJWB_PROJECT_COPY to achieve this.

I could create project but, it will be created without status object and hence can't be seen in CJ20n

We need to run program CNSTATUS to change the staus

 

Can we create project with status object (WRT template) without running above program? by using CJWB_PROJECT_COPY

If not, please let me know is there any other FM/BAPI to create WRT project

 

Thanks and Regards,

Prabhu