Dear All,

 

At the time of PR value change after creation of PO budget exceeded error is not appearing even though the PR value exceeds the budget. But at the time of changing the same value in PO, budget exceeded error is appearing.


List of steps:


PR created.

PR released

PO created with reference to PR and released.

PR value changed to a value more than the available budget - No budget exceeded error.

PO value changed in accordance with the PR - System throwing the budget exceeded error.

 

Now the issue is why the system bypassed the budget exceeded error at the time of PR value change and only giving the error at the time of PO value change. Also, we observed that while changing the quantity in PR which results in exceeding budget, system is giving the error. But while changing the value system is not giving the budget exceeded error.

 

Your inputs will be highly appreciated. Thanks in advance.