Hi experts
I have used the functionality "Maximum of 67(100) days copied as duration of activity".
I attached a component whose planned delivery time is 100 days.
However system assigned a different value.
The following information is populated by system:
Maximum of 67(100) days copied as duration of activity 0030
Message no. CN747
Diagnosis
You want to adjust the duration of a network activity to the maximum delivery time or replenishment lead time of all allocated material components.
System Response
The system only calculates using the allocated material components that have the indicator Alignment finish date set. The maximum duration comes from
the planned delivery time when the material components are procured externally
the total replenishment lead time when the material components are produced internally or the in-house production time if the total replenishment lead time is not maintained in the material master
Procedure
Make sure that the Alignment finish date indicator on the component detail screen of the activity is set for all material components allocated to the activity.
I wish experts to comment
warm regards
ramSiva