Procurement on one WBS but Consumption on another WBS

$
0
0

HI Friends,

 

 

My client is having one specific requirement, that is ..my client buys bulk materials at one time for the whole project then they will consume to the respective WBS where ever it requires at the time of execution.

 

 

 

 

Now here they are asking for budget control at the time bulk material procuring and they are asking for the consumed material actual cost on the respective WBS elements. Here I ran the test case like for one WBS I have made P.R (account assign. cate. 'Q') - PO - GRN then actual cost is coming at that place, then I consumed to the required WBS, at this time WBS is asking for the buget...but for the same material I have already assigned to earlier WBS where I bought as bulk, if i assign budget again the plan value will get double and this material procurement and consumption is not happening in the same hierarchy (if it is in same hierarchy it will work)

 

                                              

 

                                                    WBS       -      A (Cement)

 

                                                    WBS       -      B (Construction)

               

                                                    WBS       -      B-1 (Excavation)

 

In the above example I am procuring cement at WBS - A  level and I want to consume to the WBS  - B-1 level.

 

Services also they are doing in the same way ,,

 

could any one please suggest me the solution to do this..

 

 

 

Thanks & Regards,

 

Srikanth.