Currency issue in S_ALR_87013558 report.

$
0
0


Hi Experts,

I have an issue here with 558 report, budgeting has been done in CAD currency and PR has been aslo made in CAD.

 

But when i run this report i get the main budget in CAD, while commitment, assigned and available shows in USD.

 

It should come in CAD, i also tried to change the currency in 558 report via currency symbol, that is converting USD to CAD but at the same time it converts main budget (which was already in CAD) again to another value based on that conversion rate its converting to commitment.

 

I have been through all the posts on SCN, but couldnt find any precise answer.

 

Please help me getting the uniform values in 558 report.

 

Thanks,

Vindhesh