Quantcast
Channel: SCN : Discussion List - SAP Project Systems (SAP PS)
Viewing all articles
Browse latest Browse all 2586

Not able to carryforward budget from one fiscal year to another fiscal year

$
0
0

Dear All,

 

I am facing a problem in my project.

I m trying to forward my budget from one fiscal year to another fiscal year. Using t-code : CJCO.

Total release budget is 300000.

Assigned value is showing in s_alr_87013558 is 250000.

Actual value is 200000.

Commit value is -- nil

Rem. order plan  -- 50000.

Rem. budget -- 50000.

 

I have checked and verified the actual value in CJI3, its same as showing in alr report.

 

But in CJCO, while trying to carry forward budget, system showing the actual value is more than my budget 320000, which m not able to get.

I have tried all possible report but still not getting said value of actual.

 

I hv run all reconstruct t-codes also, but the result is still same.

 

Please tell me what to do now..

 

 

Regards,

 

Narender Kumar


Viewing all articles
Browse latest Browse all 2586

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>