Hi.
We are having some trouble at work. We create projects with all the steps needed (CJ01, CJ40, CJ30, IMCCP3, CJ32, CJBV, ME12N and CJ02) and assign each WBS element to ONE company code. However, when employees create a purchase order with ME23N, sometimes they choose one WBS element and choose some other company code. This causes trouble later in the process.
What can I do to restrict the WBS element they choose to the company code with which it was created or do it the other way around; restrict the company code they choose depending on the WBS element (One WBS element is picked, only one option for company code remains).
Examples
Restrict company code depending on WBS element.
They choose WBS element X, they HAVE TO choose company code X.
(Currently they can choose any company code they want)