Unable to update revenue plan values in Easy Cost Planning

$
0
0

Hi,

 

Business maintains planned costs and revenues on WBS element using Easy Cost Planning tool. But for one of the WBS element system is not allowing to update/add planned revenue line items.User is able to update the planned costs for this WBS element.

 

The Legend in Easy Cost Planning screen is Non-Changeable Cost Estimate.

The status of WBS is REL,ACPT(Order Accepted),NSCH(Not Scheduled - Forecast Dates),RESA(Result Analysis Carried out).

 

We have checked all the business process and all the revenue planning is allowed.

Please guide us on how to resolve this issue.