Activity Rates for Cost Center
Hi All, We had loaded activity rates for several cost centers for 2014 at the end of 2013. Is there a way to see if the rates have been change during the year and if so when they were changed and by...
View ArticleBudget Translation Customizing
Hi Experts,Share your thoughts & comments on budget translation.Budget is maintained on Project for over all in AUD. When actual cost is captured for current year through a PO with AUD as...
View ArticleLast Activity 100 % confirmed tables and links for BIBO reports.
dear All, i want to get the project status by knowing the last activity fully confirmed in CJ20N. please suggest me the tables and links to get the last activity in the project which is fully confirmed...
View ArticleSAP PS budgeting from IM
Hi All, Our requirement demands creating two IM program structure for CAPEX and R&D.Scenario: -IM Program structure is only used to Budget the Projects. -Let's say R&D has a Budget of 20...
View ArticleSystem doesnt compare dates of PD in top down scheduling
Hi All, I have a query. In a project structure, at project definition i am using scheduling scenario - Top Down . There is a 4 level of WBSEs and network/activites assigned to the 4th level WBSEs ....
View ArticleHow is a Value Category added to a Project ?
Hello Everyone, I am trying to determine if using Value Categories are beneficial for my client for Project Systems and Plant Maintenance.. 1.The value categories have been created and maintained in...
View ArticleActuals are not updating in PPB
Dear all, I am getting an issue related to PPB. After posting partial confirmation on activity i am trying to see the actual at gantt chart by selecting the actual in set of dates/ view. I also saved...
View ArticleCustomizing FD01 and FB70 using SAP PS Class cnd Characteristics
My client has a requirement where we need to customize the Customer Master (FD01) screen and the Invoice Posting Screen (FB70). A few additional fields have to be added by creating a separate tab. I...
View ArticleCancell or revere PO commitment line items
Hello Gurus, Here is my requirement, I want revoke or reverse or cancel my PO commitment line items. which partially confirmed. like QtyEachTotal valuePO Commitment1100100PO Actual0.9510095Remaining...
View ArticleCalculation of start date with backward scheduling
Dear all, I am facing an issue related to backward scheduling. I have requirement in which whenever backward scheduling is used, system should calculate from last activity to first for calculation of...
View ArticleProject Progress against Activity Confirmation
Hi All , What is steps to see/ Configuration Project Progress against Activity confirmation by Progress analysis . Also want to know how to see Graphical View for the same I read lots of document...
View ArticleInvoicing a PO on Activity Confirmation
Fellow Consultants , We are creating a PO with respect to Project/WBS . The Project will have Activities that Vendor is supposed to Complete for the created PO. The vendor will give Confirmation on...
View Articletable for WBS status change with date
Hi, Please assist me with a table name which should have WBS status with date on which statis was changed. Thanks,Manish.
View ArticleAuthorization Control of PS Reports
Dear All, We are tyring to do reporting restriction between two departments in standard PS cost and revenue reports.The diffrence between two departments are1>Coding Mask2>Profilt...
View Article0500 Adjustment by Follow-on Document
Hi Guys, In Budcon report we usually have 100 and 200 (original , reduction). In my case its 100 and 500 (original and adjustment by follow on document). On checking the PR , I found that PR was...
View ArticleOrder Engineering Process
Hi Everyone The scenario is described as below. The order engineering process is something like keep changing until the moment of delivery. The customer places an order for a product for certain...
View ArticleNegative Costs in cji3 Report
Hi ,We are presently facing an issue with negative costs in cji3 report (Actual Cost Line Item Report). How to get rid of these negative balances? What should be done to ensure that there are actuals...
View ArticleProjects getting Locked automatically
Hello Guruz, I was scheduling and editing my project in CJ2B, SAVEd my changes, when i tried to edit the same project again I get a message "Project is being edited by User(me) and is locked.", I...
View ArticleFM for Planned Total values of a WBS
Hi All, Looking for an FM which can give me Planned Total values of a WBS element (that means, of that particular WBS element and all the objects below that WBS, including WBS, activities, etc.) just...
View ArticleSystem doesnt compare dates of PD in top down scheduling
Hi All, I have a query. In a project structure, at project definition i am using scheduling scenario - Top Down . There is a 4 level of WBSEs and network/activites assigned to the 4th level WBSEs ....
View Article