Hello all
We have one case where we add a Investment program and budget for 2013 with 10 thousand EUR .
The project related is scheduled in network header from 2013 until 2015.
We have two activities in this network header. First activity is scheduled for 2013 in the constraints and the value assigned is 7993 EUR.
We have the second activity scheduled to 2014 in the constraints and the value assigned is 7993 EUR.
We have availability control activated for each year and the tolerance to requisition with error message if the budget is exceed in 100%.
We didn't receive any error message during the creation of this requisition although we don't have budget and the availability is activated.
Do you if there are some customization that must be consider or some functionality that can be implemented to avoid this kind of situation ?
Regards
Cristina Romanato