Use of release stop indicator function in milestone

$
0
0

Hi All,

 

Can anyone tell me what is the exact use of 'release stop indicator' function in milestone. For example, I have created 4 Activity:

 

  • Activity 1  Relation FS
  • Activity 2  Relation FS
  • Activity 3  Relation FS
  • Activity 4  Relation FS

 

So after 2nd activity I put milestone 'release stop indicator' and when I'm going to release all activity by releasing network. 1st and 2nd activity is released after that I got I 'release stop indicator message' and my 3rd and 4th activity also released which should not be released as I already put 'release stop indicator' milestone on 3rd actvity so system should releasing all activity after 3rd acivity.

 

So kindly tell me how I resolve this issue.

 

 